Nahom Tesfatsion 2024 Summary |
|||
Name |
Date |
Week Ending |
This week |
Office Date |
Obstacles |
---|---|---|---|---|---|
Nahom Tesfatsion | 9/27/2024 | Friday, September 27, 2024 | ***** New integrated website for SLT/EWL ***** TAC-4013: Update Plot and data path for Sea Level Trends and Extremes (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Development is Done. Testing on Dev TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in Done. Testing on Dev ***** Extreme Water Level ***** TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: On Hold TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 9/20/2024 | Friday, September 20, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in progress ***** Extreme Water Level ***** TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 9/13/2024 | Friday, September 13, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Done TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in progress ***** Extreme Water Level ***** TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 9/6/2024 | Friday, September 6, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation done, Testing on Dev TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: New requirement; Implementation in progress ***** Extreme Water Level ***** TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) Status: Implementation in progress TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 8/30/2024 | Friday, August 30, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress, TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: New requirement; Implementation in progress ***** Extreme Water Level ***** TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 8/23/2024 | Friday, August 23, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3957: Update Sea Level Trends and Extremes content (Estimate days to completion: 3d / Actual days to completion: 2d 2h) Status: Done and Closed TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: New requirement; Implementation in progress ***** Extreme Water Level ***** TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: 4d) - Status: Closed TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) | Wednesday, August 21, 2024 | None |
Nahom Tesfatsion | 8/16/2024 | Friday, August 16, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: New requirement; Implementation in progress TAC-3957: Update Sea Level Trends and Extremes content (Estimate days to completion: 1wk / Actual days to completion: TBD) Status: Implementation in progress ***** Extreme Water Level ***** TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: 4d) - Status: Completed. Moved for CCB review TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress Not yet Started tasks: TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) | Friday, August 16, 2024 | None |
Nahom Tesfatsion | 8/9/2024 | Friday, August 9, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Testing on Dev TAC-3957: Update Sea Level Trends and Extremes content (Estimate days to completion: 1wk / Actual days to completion: TBD) ***** Extreme Water Level ***** TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: 1w & 2d) - Status: Moved for CCB review TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation is Done. Testing in UAT TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress Not yet Started tasks: TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) | NA | None |
Nahom Tesfatsion | 8/2/2024 | Friday, August 2, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: New requirement added, Implementation in progress TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Testing on Dev ***** Extreme Water Level ***** TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Implementation is Done. Testing in UAT TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation is Done. Testing in UAT TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) Status: Implementation in progress Not yet Started tasks: TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) TAC-3957: Update Sea Level Trends and Extremes content (Estimate days to completion: 3 d / Actual days to completion: TBD) | NA | None |
Nahom Tesfatsion | 7/26/2024 | Friday, July 26, 2024 | ***** New integrated website for SLT/EWL ***** TAC-3915: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: New requirement added, Implementation in progress TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Testing on Dev ***** Extreme Water Level ***** TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Testing in UAT TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3951: changing basemap to vector format (EWL/Integrated site) (Estimate days to completion: 3 d / Actual days to completion: TBD) - Status: Implementation in progress Not yet Started tasks: TAC-3941: plotting RFA extremes (Estimate days to completion: 4 wks / Actual days to completion: TBD) TAC-3940: remove hyperlink to Extreme Water levels for stations 8635150 and 8639348 (Estimate days to completion: 3 d / Actual days to completion: TBD) TAC-3957: Update Sea Level Trends and Extremes content (Estimate days to completion: 3 d / Actual days to completion: TBD) | NA | None |
Nahom Tesfatsion | 7/19/2024 | Friday, July 19, 2024 | *New integrated website for SLT/EWL* TAC-3914: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Testing on Dev TAC-3937: SLT/EWL landing/entry page (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in progress *Extreme Water Level* TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Testing in UAT TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress | Friday, July 19, 2024 | None |
Nahom Tesfatsion | 7/12/2024 | Friday, July 12, 2024 | TAC-3914: Add map Overlays (Estimate days to completion: 1 wks / Actual days to completion: TBD) Implementation in progress TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) Status: Testing in UAT TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) Status: Implementation in progress TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in progress | Friday, July 12, 2024 | None |
Nahom Tesfatsion | 7/5/2024 | Friday, July 5, 2024 | TAC-3917: Update Extreme Water Level State Selection - Status: Testing in UAT TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Testing in UAT TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) - Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 6/28/2024 | Friday, June 28, 2024 | TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Testing in UAT TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in progress Integrated both est and sltrends plots | Friday, June 28, 2024 | None |
Nahom Tesfatsion | 6/21/2024 | Friday, June 21, 2024 | TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Testing in UAT TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 6/14/2024 | Friday, June 14, 2024 | TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Testing in UAT TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress, Integrated Sea Level Trends TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) | Friday, June 14, 2024 | None |
Nahom Tesfatsion | 6/7/2024 | Friday, June 7, 2024 | TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3917: Update Extreme Water Level State Selection (Estimate days to completion: 1 wks / Actual days to completion: TBD) | NA | No Obstacles |
Nahom Tesfatsion | 5/31/2024 | Friday, May 31, 2024 | TAC-3870: Remove unique language for four stations (Estimate days to completion: 3 days / Actual days to completion: 1d) - Status: Completed TAC-3835: Update language on EWL pages (Estimate days to completion: 2 wks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 4 wks / Actual days to completion: TBD) - Status: Implementation in progress | Friday, May 31, 2024 | None |
Nahom Tesfatsion | 5/24/2024 | Friday, May 24, 2024 | TAC-3537: Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: 2wks) -Status: Completed TAC-3870: Remove unique language for four stations (Estimate days to completion: 3 days / Actual days to completion: TBD) - Status: Testing on UAT TAC-3835: Update language on EWL pages (Estimate days to completion: 2 weeks / Actual days to completion: TBD) - Status: Implementation in progress TAC-3914: master ticket - new integrated website for SLT/EWL (Estimate days to completion: 5 weeks / Actual days to completion: TBD) - Status: Implementation in progress | NA | None |
Nahom Tesfatsion | 5/17/2024 | Friday, May 17, 2024 | TAC-3537: Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) - Status: Resolved in testing - TAC-3870: Remove unique language for four stations (Estimate days to completion: 3 days / Actual days to completion: TBD) - Status: Testing on UAT - TAC-3835 Update language on EWL pages (Estimate days to completion: 2w days / Actual days to completion: TBD) - Status: Implementation in progress Worked on the prototype for integrating Sea Level Trends and Extremes. | NA | No obstacles |
Nahom Tesfatsion | 5/10/2024 | Friday, May 10, 2024 | TAC-3537: Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) - Status: Testing on UAT - TAC-3870: Remove unique language for four stations (Estimate days to completion: 3 days / Actual days to completion: TBD) - Status: Testing on UAT - TAC-3835 Update language on EWL pages (Estimate days to completion: 2w days / Actual days to completion: TBD) | Thursday, May 09, 2024 | No obstacles |
Nahom Tesfatsion | 5/3/2024 | Friday, May 3, 2024 | TAC-3827 - Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) Status: Implementation in done; Working with Chris(Scientist) to test my implementation TAC-3835 - Update language on EWL pages (Estimate days to completion: 2w days / Actual days to completion: TBD) Status: Started implementation | NA | No Obstacles |
Nahom Tesfatsion | 4/26/2024 | Friday, April 26, 2024 | TAC-3827 - Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) Status: Implementation is done, Testing done on Dev and in progress on implementing feedback. (note: Requirement has been extended to download files and page content for Port Mansfield EWL station) | Friday, April 26, 2024 | Navigating the requirement was challenging but No obstacles |
Nahom Tesfatsion | 4/19/2024 | Friday, April 19, 2024 | TAC-3827 - Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) Status: Implementation of the Extreme Water Levels Plot is done, and in progress to implement on the rest of the plots | NA | No obstacles |
Nahom Tesfatsion | 4/12/2024 | Friday, April 12, 2024 | TAC-3827: Port Mansfield EWL (Completed) TAC-3827 - Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) Status: implementation is in progress | Friday, April 12, 2024 | No obstacles |
Nahom Tesfatsion | 4/5/2024 | Friday, April 5, 2024 | This week I have worked on the following: TAC-3803 - Provide a link to one week of data around extreme events (Estimate days to completion: 3w / Actual days to completion: 3w) Status: Passed on UAT, Ready to deploy into Production TAC-3827 - Port Mansfield EWL (Estimate days to completion: 5-6 days / Actual days to completion: TBD) Status: Gathered the requirements, implementation is in progress | Friday, April 5, 2024 | No obstacles |
Nahom Tesfatsion | 3/29/2024 | Friday, March 29, 2024 | This week I have worked on the following: TAC-3803 - Provide a link to one week of data around extreme events - I've wrapped up the task locally and am now in the testing phase to ensure everything runs smoothly. Next, I'll be partnering with Miciaha to seamlessly deploy my changes. | Tuesday, March 26, 2024 | Yes, I encountered the following obstacle: - Unable to log work on my Jira ticket due to permissions issues. A ticket has been raised (SUPPORT-31379) and is awaiting processing. |
Nahom Tesfatsion | 3/22/2024 | Friday, March 22, 2024 | This week I have worked on the following: - Configure personal directory in `/home/net` under Linux environmental (Tectia) - Set up a local development environment of Extreme Water Level - TAC-3803 - Provide a link to one week of data around extreme events - In progress, I am gathering the requirements and navigating the codebase to implement the request. | Wednesday, March 20, 2024 | Below are the things I will be working on next to resolve any access blockage: - Establish a Cloud 9 account. (SUPPORT-31373) - Request to Move tickets and Log work under JIRA (SUPPORT-31379) |
Nahom Tesfatsion | 3/15/2024 | Friday, March 15, 2024 | This week I have worked on the following: - Set up SVN for version control. - Configured Linux environment via Tectia. - Received JIRA and Tectia orientation from Petros. - Reviewed Extreme Water Level project documentation. | Friday, March 15, 2024 | Below are the things I will be working on next to resolve any access blockage: - Configure personal directory in `/home/net` under Linux environmental (Tectia) - Establish a Cloud 9 account. - Resolve the "Log work" button visibility in JIRA. - Set up a local development environment of Extreme Water Level - Manage assigned tickets. |
Nahom Tesfatsion | 3/8/2024 | Friday, March 8, 2024 | This week, I was able to work with the window and infrastructure team to set up my computer and account access. Ticket: https://support.co-ops.nos.noaa.gov/jira/browse/SUPPORT-31044 So far I have again access to: - Access to Gmail - Connect to VPN - Access to JIRA - Access to Confluence - Received User and Password for Sybase DB - Rapid SQL Need help to setup the following accounts: - SVN - Linux Environment, accessing through Tectia - Any other account that I may need I am reaching out to Mike and Tonya to help me gaining access with the rest. In the mean time, I am working on completing my Checklist with Petros and working with the Dev team under Extreme Water Levels project. | Tuesday, March 5, 2024 | Beside getting the access of what I have listed above, there is no other obstacles. |